September, 2000. These are pictures of the land itself, before any clearing has begun. There are three parcels included with this property, totalling 6.7 acres. The land is wooded with live oak, scrub oak and an occasional pine tree. The soil is white sand, almost the color of sugar.
November, 2000. These are pictures of my house being built at the factory. It was very hard to take pictures since the house was in pieces with plastic covering up many of the areas. I was unable to take pictures of the bedrooms and baths, but I was able to get several shots of the kitchen, living room and outside the house.
December, 2000. The land clearing has finally begun. On the red tractor is my contractor, Mike, with his son Justin. On the yellow tractor is a man named Todd who was hired to regrade the land after the first subcontractor left before the job was completely done. I was promised that my house would be done by Thanksgiving. The contractor is telling me now that I will be in the home by Christmas!
January 10, 2001. Finally work has begun again. I had to make several calls to the Department of Consumer Affairs, Liberty Homes and an attorney in order to get things moving again! Things aren't looking too good these days with Harvey Homes.....
February 3, 2001. The work has stopped again. Jeff Harvey will not return my calls, nor my attorney's calls. The last time we saw anyone from Harvey Homes was on January 25, when they abandoned the house at the gravel pit across the street.
March 16, 2001. Harvey Homes has never returned. My lawyer fired him on March 6 and made arrangements with the bank for me to finish the work myself. I'm waiting for checks from the bank before doing anything more. I did, however, pay to have the driveway widened and have the house delivered to the site. Here are the pics!
March 28, 2001. I've received the first three checks from the bank. The foundation was treated for termites on March 26. Today is the day the house will be set!
April, 2001. Siding has been installed and plumbing hooked up. I'm working with the Seminole County Building Department to get all the inspections. I've been forced to do all the painting and caulking myself, since I could not afford to pay someone to do this.
May, 2001. The house is almost finished, and construction on the garage is continuing. I chose to have the entire house tiled. I cannot get the CO until the flooring is finished and the building department passes my final building inspection. I also need to have my well water tested.
February, 2002. The house has been finished since June, 2001. Harvey put a fradulent lien on the property after he discovered that I finished the house myself. We've been battling in court for almost a year now. We are scheduled to go to trial in March, 2002. In addition to ripping me off, he's apparently been very busy doing similar things to other folks up in Citrus County. He's currently being investigated by the Citrus County Sheriff's Department, the State Attorney and the Attorney General for numerous criminal and civil charges, including forgery. Let's hope he goes to jail!
Here are some pictures. I'm trying to decide if this new light fixture is appropriate for the house. The electrical is dangling, since it is not permanently installed yet. The home exterior is almost finished. Just a few things remain, including staining the front porch and finishing the back deck.
These pictures were taken in March and April, 2002. The house is pretty much complete. I still need to do some touch up painting and continue working on my flower beds. The home and property were successfully refinanced.